CBH Group

RDH was contracted by CBH to construct Temporary Grain Storage Facilities in Narngulu in WA’s Mid West in order to manage record-breaking harvest volumes and enhance supply chain efficiencies.

 

Project scope:

Construction of Peak Planning bulkheads to meet the 2025/26 Harvest Program consisting of:

  • Bulk earthworks

  • Drainage works

  • Pavement and hardstand construction works

  • Provide set out points for open bulkhead (OBH) frames

 

Construction works:

  • Bulk Earthworks

    • Clearing

    • Topsoil removal

    • Foundation preparation

    • Embankment construction

  • Drainage Works

    • Construction of stormwater drains around roads

    • Connection of stormwater drains to a newly constructed basin

    • Supply and install of culverts

  • Pavement and Hardstand Construction Works

    • Supply and install of ridge gravel including cement stabilisation for access roads, cross overs, DOG road and underside of OBH frames

    • Construct hardstand area for tarp roads and within the OBH frames area

  • Other

    • Provide set out points for OBH frames

Project completed: December 2025

Lise Doyle