RDH was contracted by CBH to construct Temporary Grain Storage Facilities in Narngulu in WA’s Mid West in order to manage record-breaking harvest volumes and enhance supply chain efficiencies.
Project scope:
Construction of Peak Planning bulkheads to meet the 2025/26 Harvest Program consisting of:
Bulk earthworks
Drainage works
Pavement and hardstand construction works
Provide set out points for open bulkhead (OBH) frames
Construction works:
Bulk Earthworks
Clearing
Topsoil removal
Foundation preparation
Embankment construction
Drainage Works
Construction of stormwater drains around roads
Connection of stormwater drains to a newly constructed basin
Supply and install of culverts
Pavement and Hardstand Construction Works
Supply and install of ridge gravel including cement stabilisation for access roads, cross overs, DOG road and underside of OBH frames
Construct hardstand area for tarp roads and within the OBH frames area
Other
Provide set out points for OBH frames
Project completed: December 2025