CBH Group
RDH was contracted by CBH to construct a Temporary Grain Storage Facility in Carnamah in WA’s Mid West in order to manage record-breaking harvest volumes and enhance supply chain efficiencies.
Project scope of works:
Construction of bulk earthworks pad and access roads
Construct pavement layers
Construct and install drainage
Construction works:
Site clearing and topsoil stripping
Cut to fill
Embankment construction
Rock excavation
Import of fill
Install drainage culverts
Form drains and sump
Cement stabilisation worksConstruct pavement layers
Install signage
Provide set out points for open bulkhead (OBH) frames
Project completed: October 2025